TOPIC: Evaluate C/R before submitting it by PM

Evaluate C/R before submitting it by PM 3 years 10 months ago #25597

  • Mohamad Najib
  • Mohamad Najib's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hi,
I am not sure whether PMI philosophy asks the PM to evaluate the impact of C/R before raising it or after? i.e. the PM is part of the CCB, so shall he/she evaluate the impact before raising the C/R or after if it will come from his/her side?
I think If it is not by his/her side, i.e vendors, or stakeholder, it is clear that it will be part of the CCB review .
But if it is by PM, he /she should evaluate the impact (scope/cost/schedule/risk) before raising the request, is not?

Evaluate C/R before submitting it by PM 3 years 10 months ago #25739

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
Hi Mohamad, I would (in real life) understand the impact of the change before raising the change request. Otherwise, it can't be discussed, approved or rejected as we won't know what the implications would be. Someone can ask for a change at any point, but I wouldn't take it to the CCB without knowing what the impact would be.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login