fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Can you have multiple timeboxes in 1 iteration

Can you have multiple timeboxes in 1 iteration 3 years 11 months ago #25432

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
Can you have multiple time boxes in 1 iteration?

Can you have multiple timeboxes in 1 iteration 3 years 11 months ago #25456

  • PMP Aspirant
  • PMP Aspirant's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 68
  • Karma: 1
  • Thank you received: 12
Hi Sharon,
Can you explain what is your definition of a "timebox"?

Can you have multiple timeboxes in 1 iteration 3 years 11 months ago #25462

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
On page 182 of the PM BOK for release and iteration length. I saw a question in prepcast that gave a scenario and timebox was the answer. So I'm wondering if a time box is considered 1 iteration or can you have more than 1 timebox per iteration.
Last edit: by Sharon S.

Can you have multiple timeboxes in 1 iteration 3 years 11 months ago #25463

  • PMP Aspirant
  • PMP Aspirant's Avatar
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 68
  • Karma: 1
  • Thank you received: 12
Timeboxing is a concept, for example daily standups are generally of 15 minute duration so we can say that we have "timeboxed" the daily standups to 15 minutes.
Similarly other Scrum ceremonies like Sprint/Iteration planning, Sprint/Iteration Review & Retrospectives are all "timeboxed" to 1 week, 2 weeks or 4 weeks so timeboxing is a concept of putting a limit to an activity.
The following user(s) said Thank You: Sharon S

Can you have multiple timeboxes in 1 iteration 3 years 11 months ago #25468

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
Thank you for the detailed response. I'll remember now that timeboxing is a "a concept of putting a limit to an activity." That definitely clears it up. Thanks!
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login