fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Matrix environment

Matrix environment 4 years 22 hours ago #24680

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
I see many questions, where it says 'matrix' environment. By that, does it mean a weak matrix environment, where the project manager has not much control. Please clarify.

Matrix environment 3 years 11 months ago #24731

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
I take it to mean a situation where the project manager does not have line management responsibility for the team, unless the type of matrix is specifically mentioned.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

Matrix environment 3 years 11 months ago #24736

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Hi Elizabeth, thank you.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login