Hey all! I got this question during a timed PM PrepCast quiz (Q ID# 612237):
What is the key benefit of developing a charter for a project?
A ) Providing the project manager with the formal authority to manage the project
B ) Creating a contract between the project manager and the performing organization
C ) Linking the project to the strategic objectives of the performing organization
D ) Creating a comprehensive document that defines the basis of all project work
I had selected A, but the correct answer is C. Reading the details for A, I now understand that providing authority to the PM is outlined in the Charter, but is not the key benefit. But I am confused how the answer is C ("One of the key benefits of developing the project charter is to provide a direct link between the project and the strategic objectives of the organization"). Doesn't the Business Case outline how the project/product aligns with the organization's strategic goals?
Apologies if this question has been asked before - I searched the forum but couldn't find a response that addressed this directly. Appreciate the help!