fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Project Stakeholder Management - Question

Project Stakeholder Management - Question 4 years 1 week ago #24387

  • Andrew Payerl
  • Andrew Payerl's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 1
Hello,

I was wondering how the Stakeholder Engagement Plan can be an Input to the Identify Stakeholders process, when the Stakeholder Engagement Plan is the main output of the next process, Plan Stakeholder Engagement. Is this similar to the Change Requests output for the Identify Stakeholders process, where this only happens after the first iteration of identifying stakeholders?

My thinking is that during the Identify Stakeholders process, the Stakeholder Engagement Plan wouldn't be developed yet. Can someone clarify?

Thank you,

Project Stakeholder Management - Question 4 years 1 week ago #24390

  • Charlie
  • Charlie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 36
  • Thank you received: 3
Hi Andrew,
I guess that this means that the stakeholder engagement plan is input to any iteration of the identify stakeholders that occur after the plan is available. Since identify stakeholders is a process that occurs throughout the project lifecycle more iterations are likely to take place
Hope it helps
Carlo
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login