TOPIC: Question regarding when a change request is needed.

Question regarding when a change request is needed. 4 years 1 month ago #23864

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Which all documents need a change request for an update?

I know that once Project Management plan is approved, any change to the baseline or management plan will need a change request to update that document.

But if we are changing a Project document such as Risk register or Stakeholder register or Lessons Learned register, do we need to submit a change request? I believe we don't need one. Please confirm.
Last edit: by Rahul Vadakke Veetil PMP.

Question regarding when a change request is needed. 4 years 1 month ago #23869

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
I can't say for sure what the exam would require you to say, but in 'real life' I wouldn't submit a change request for changes to working documents like the risk register, stakeholder register or lessons learned register. These are documents that could be updated far too frequently to make the change request process viable.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
The following user(s) said Thank You: Rahul Vadakke Veetil PMP
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login