Cost functions scenarios 4 years 1 month ago #23774

  • Mirit Ben Harush shmilovich
  • Mirit Ben Harush shmilovich's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
How can i pick the right function to the question?
for example:
TCPI - (BAC-EV)/ (BAC-AC) OR (BAC-EV)/(EAC-AC)
What question should be asked in order to understand what to choose?

Thanks!

Cost functions scenarios 4 years 1 month ago #23775

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
MIrit:

The question will provide you with all of the variables you need to select the correct equation or it will be a 2-step problem solving question. On my PMP exam, however, I did not encounter any of more advanced formule though.

Good luck!

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
The following user(s) said Thank You: Mirit Ben Harush shmilovich

Cost functions scenarios 4 years 1 month ago #23784

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
Usually the questions in simulator mention, if it is to be calculated to original budget or it would say original budget is not valid, so calculated TCPI for new forecasted value. usually very clear.
The following user(s) said Thank You: Mirit Ben Harush shmilovich
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login