fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Calculating Critical Path variance

Calculating Critical Path variance 4 years 1 month ago #23686

  • Calculating Critical Path variance
  • Calculating Critical Path variance's Avatar Topic Author
  • Visitor
  • Visitor
I would be sincerely grateful if you could answer the following question. After calculating task duration with a PERT three point estimate do you include lag on the total task duration to calculate variance or just the PERT estimate without the lag time? Hope this is clear. Many thanks for your help in this matter.
Regards
Paul Evans

Calculating Critical Path variance 4 years 1 month ago #23688

  • Eric Wanyutu Kahiga, PMP, PMI-ACP
  • Eric Wanyutu Kahiga, PMP, PMI-ACP's Avatar
  • Offline
  • Expert Boarder
  • Expert Boarder
  • Posts: 84
  • Karma: 4
  • Thank you received: 28
Hi Paul Evans.
To calculate task duration using the Project Evaluation Review Technique (PERT), three-point estimate you need to have 3 parameters which are:-
1) Optimistic duration estimate = a
2) Pessimistic duration estimate = b
3) Realistic duration estimate = m
To get the task duration, you give a weight of 4 to the realistic time duration (this means to multiply it by 4) and add the other 2 parameters and then divide the answer by six.

Therefore:- Estimated Time (T) = (a + b + m)/6

Variance is then given by the formula:-
Variance x Variance = (a-b)(a-b) x 1/6

(Please note that due to my inability to paste fractions and superscript to my answer above, I have made the formula for variance to be a bit more complex than it really is so that it can remain mathematically correct. The right side denotes the square of variance and the left side denotes be the square of the difference of the Pessimistic and Optimistic time divided by 6)

As you can see from the formulas above, the lag time does not feature in the workings and to answer your question; lag on the total task duration is not used to calculate variance. I hope that I have answered your question.
Eric Wanyutu

Calculating Critical Path variance 4 years 1 month ago #23690

  • Paul Evans
  • Paul Evans's Avatar Topic Author
  • Visitor
  • Visitor
Many thanks for your prompt reply and clear explanation.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login