control costs related query 4 years 1 month ago #23670

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
recently two of your team members went on a customer visit. You were in the process of making sure the expenditures submitted by them were accurate. what process are you currently performing?

1) control resources
2) control costs
3) control procurements
4) monitor risks

the correct answer according to eduhubspot is 1. But isnt control costs associated with physical resources and not team/staff? I feel option 2 is more accurate...thgts please

control costs related query 4 years 1 month ago #23701

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
can anyone please help clarify this?

control costs related query 4 years 1 month ago #23712

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
The process "Control Resources" refers to physical resources. This would be things like material / equipment, so it certainly doesn't fit based on the question. I think control costs is the best answer of the options provided.
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Deepti Bhattacharya
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login