TOPIC: Aquire Resource/Control resource related query

Aquire Resource/Control resource related query 4 years 1 month ago #23666

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
PM Complained to project Sponsor that he did not get correct number of resources as planned. Sponsor agrees the PM's complaint is genuine and decides to cancel the project. which process would have prevented this extreme step from sponsor
1) Acquire resources
2) control resources
3) manager team
4) estimate activity resources

I though it was 2, but correct answer is 1. The explanation given in eduhubspot is not satisfactory, as it eliminated 2 based on it is for physical resource and not human resource. But no where in question its says type of resource.

Your thoughts please?

Aquire Resource/Control resource related query 4 years 1 month ago #23683

  • Felix Kamanga, PMP
  • Felix Kamanga, PMP's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 67
  • Karma: 5
  • Thank you received: 14
Hi Deepti,

Indeed, Control Resources is related to physical resources, and Manage Teams is related to human resources.
Felix Kamanga, PMP
Community Moderator
The following user(s) said Thank You: Deepti Bhattacharya

Aquire Resource/Control resource related query 4 years 1 month ago #23684

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
@felix can then control resources be right answer? consider we check resource availability during control resources, and if any deviation we could have taken necessary action and not wait till acquire resource step, to realize resources are not available?

Aquire Resource/Control resource related query 4 years 1 month ago #23699

  • Felix Kamanga, PMP
  • Felix Kamanga, PMP's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 67
  • Karma: 5
  • Thank you received: 14
The correct answer is clearly (1) because the resources needed to complete project work are obtained during the process of Aquire Resources.
The planned number of resources must be obtained here, and that is concerning both human and physical resources.
Please check in the PMBOK 6th Edition, on page 328.
I hope this could help.
Felix Kamanga, PMP
Community Moderator
The following user(s) said Thank You: Deepti Bhattacharya
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login