fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Corrective action process

Corrective action process 4 years 2 months ago #23554

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
You have scheduled regular weekly team meetings with project team members. Things have been going according to plan and there have been no variances till date with respect to the work performance baselines. A site engineer reports that he had to perform a couple of corrective actions, but they were not logged. As a Project Manager, what should you do?
SELECT THE CORRECT ANSWER

Reprimand the team member for not documenting the corrective action
Reprimand the team member and ensure the corrective action is reverted
Do nothing
Document the corrective actions performed in the historical records

Correct Option: D


I chose b, because I felt, corrective action though important needs to be done only after proper change control., so revert the changes, follow correct process then do the approved corrective changes and update historical records. Am i wrong?

Corrective action process 4 years 2 months ago #23568

  • Harry Elston
  • Harry Elston's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 473
  • Karma: 27
  • Thank you received: 146
Deepti:

Are you getting these questions from the PrepCast exam simulator? If so, I believe that explanations are given for each question. If you're not, then you need to speak to the company that wrote the question.

But, to answer your immediate question:

The correct answer is D. No "reprimands" are required or desired. A corrective action corrects a defect in process or product, and are performed without change requests. Even more so if the corrective action will not impact project baselines. So, A and B are eliminated. "Do nothing" is NEVER an apropiarte answer for the PMP exam., so C is eliminated as well.

Harry
+++++
Harry J. Elston, Ph.D., CIH, PMP
The following user(s) said Thank You: Deepti Bhattacharya

Corrective action process 4 years 2 months ago #23577

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
No they are from simplilearn, unlike prepcast simulator they dont give explanations for each question.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login