I have seen the following equations for EAC

EAC = BAC / CPI

EAC = AC + (BAC - EV)

EAC = AC + ((BAC - EV) / (CPI x SPI))

Can you please clarify the criterion by which one of these can be used? Like, at which situation, should we use one particular formula from these?

Criterion for equations for Estimate At Completion (EAC) ? 4 years 3 months ago #23370

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
EAC = BAC / CPI
Use this when you have a trend on your project you expect to continue, and does not pose issue to the project.

EAC = AC + (BAC - EV)
Use this if you had a deviation on your project, but going forward you expect the project to be brought back in alignment with plan.

EAC = AC + ((BAC - EV) / (CPI x SPI))
Use this if schedule performance must be considered (e.g. if project is behind schedule).
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator

Criterion for equations for Estimate At Completion (EAC) ? 4 years 3 months ago #23403

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Thank you.

Which one to use, if the CPI or SPI kept changing at random till now? Is BAC/CPI the most commonly used?
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login