TOPIC: Workaround

Workaround 4 years 2 months ago #23164

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Hi
Could you please make it clear for me.
Is workaround an unplanned response to Unknown-Unknown or Known-Unknow or both.

Thanks

Workaround 4 years 2 months ago #23171

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Mahdi,

I think workarounds will be needed to deal with an unanticipated problem, so in this respect you may look at it as an "unknown-unknown" that calls for a corrective action to «work around» that problem.
However, what if you have a known-unknown, so the risk has been identified, and possibly accepted (as part of the response strategy), but then it turns out that some corrective action is needed? I would say a workaround would also be needed in this case.

My 2 cents here. I'll be glad to hear what others think about this.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator

Workaround 4 years 2 months ago #23172

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Could you please other share their thought

Workaround 4 years 2 months ago #23250

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
I agree with Gabriella. There's nothing more I can add!
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Mahdi Seify

Workaround 4 years 2 months ago #23262

  • Mansour Ne
  • Mansour Ne's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 1
Hi everyone

I remembered question in real exam talk about workaround
It was long question and ended with this
PM needs to create workaround to deal with?
I remember only two options
1- to deal with risks that passively accepted and/or unidentified risks once it occurs
2- to deal with unidentified risks once it occurs

I got confused during the exam
But Ive chosen No1
I think it was correct

After reaserching for more info
I found the following:
Workaround used for unidentified risks and passively accepted risks

For risk are accepted actively will be dealt with a fallback

Hope this info help you to pass your exam
The following user(s) said Thank You: Mahdi Seify

Workaround 4 years 2 months ago #23283

  • Mahdi Seify
  • Mahdi Seify's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 51
  • Thank you received: 0
Thanks so much, Mansour, It is so helpful
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login