fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Does Change request require to access Contingency Reserve?

Does Change request require to access Contingency Reserve? 4 years 3 months ago #22967

  • Sharad Sinha
  • Sharad Sinha's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Karma: 1
  • Thank you received: 0
hi, Could some body tell me does 'Change request' is require to access Contingency Reserve?

Does Change request require to access Contingency Reserve? 4 years 3 months ago #22970

  • Viswa Kathir
  • Viswa Kathir's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 19
  • Karma: 1
  • Thank you received: 5
Hi,
The answer is 'No' because contingency reserves are part of baselines and hence to use the contingency reserve, change request is not needed.
The following user(s) said Thank You: Alexis Higgins
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login