TOPIC: Two questions I would like to understand

Two questions I would like to understand 4 years 3 months ago #22854

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
1) EV=200. PV=300. SPI=1. AC=250. How much is earned value?

A 50
B 100
C 200
D 450

I am confused. Isn't EV already given ? Isn't the answer 200 ? Or am I not understanding the question correctly ?

2) In which process are most resources spent?

A Project Communications Management
B Create WBS
C Direct and Manage Project Work
D Monitor and Control Project Work

I believe answer is C. Or is it A ?

Please help. Thank you.
Last edit: by Rahul Vadakke Veetil PMP.

Two questions I would like to understand 4 years 3 months ago #22855

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Rahul, don't worry: sometimes the answer is much easier than you would expect. Indeed the Earned Value is given in question 1, so the answer is C.

As for question 2, you have to keep in mind that project expenditures and resources tend to be at their minimum at the beginning of their project, increase over time to reach their peak while most of the work is carried out, and then decrease while the project moves towards its completion. Now, looking at the options provided, you can associate a process group to each of the processes listed as options:
B => Planning
C => Executing
D => Monitoring & Controlling
So, I will select C, because that is one of the 'major' processes, where most of the project work is performed, so it will be the one spending most resources.
Option A in itself is not even a process, rather being an entire knowledge area - hope my interpretation does not sound too restrictive.

As per the forum policy, I'd recommend to include information about where you found these sample questions. Thank you!

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator

Two questions I would like to understand 4 years 3 months ago #22863

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Thank you, Gabriella. Yes, I also believe option A in the second question is given just to confuse.
Last edit: by Rahul Vadakke Veetil PMP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login