TOPIC: Change Requests/ Project Management plan updates as output of many processes

Change Requests/ Project Management plan updates as output of many processes 4 years 3 months ago #22683

  • Sooraj Urothummal
  • Sooraj Urothummal's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hello,
Some processes have "Change Requests" as output and
some others have "Project Management plan updates" as output and
some of them have both "Change Requests" and "Project Management plan updates" as their output.

Given that any "project management plan update" need to go through a change request what is the distinction here in these outputs above?

Change Requests/ Project Management plan updates as output of many processes 4 years 3 months ago #22705

  • Mike Cheung, PMP
  • Mike Cheung, PMP's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 5
Good question

here's my thought
- If the output is for a process that is in the planning phase, there should only be project management plan updates (as the plan has not been approved yet and does not require a change request for an update)
- if the output is for a process in the executing and M&C phase, the project management plan updates should always be accompanied by a change request
- in the case of a few processes that are in the planning phase that has a change request and a project management plan update - it is because these are processes that might need to be revisited at any point later in the project (i.e. plan risk responses, define activities, develop schedule, plan procurement management)

Curious to hear other thoughts.
The following user(s) said Thank You: Sooraj Urothummal, Aniket Patil
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login