fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Change Request to update EEF, OPA and Project Documents

Change Request to update EEF, OPA and Project Documents 4 years 3 months ago #22663

  • Mohammad Farhan Madhwala
  • Mohammad Farhan Madhwala's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Hi All, Mine understanding is that UPDATES to EEF, OPA's, Project Documents DO NOT need a change request. Is mine understanding correct ?

Change Request to update EEF, OPA and Project Documents 4 years 3 months ago #22664

  • Vivek Sharma
  • Vivek Sharma's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 0
Right!
CR is required only for Project Management Plan and it's Components.
Refer Table 4-1 of PMBOK. All 18 Project Management Plan's component , after approval, need CR for modification. The 33 documents mentioned in same table do not need CR.
EEF by definition itself may be outside the authority of Project Manager and/or various stakeholders and hence, of course outside the authority of CCB too.
OPAs also dont need CR.

Change Request to update EEF, OPA and Project Documents 4 years 3 months ago #22665

  • Vivek Sharma
  • Vivek Sharma's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 24
  • Karma: 1
  • Thank you received: 0
BTW did you know that Requirement Management Plan is also known as Business Analysis Plan. :)
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login