TOPIC: What is the difference between cost estimates and the project budget?

What is the difference between cost estimates and the project budget? 4 years 3 months ago #22590

  • Lisa Long
  • Lisa Long's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
I'm struggling with what makes these different and needing some expert advice to clarify. It feels like the estimates and budget are the same thing?

What is the difference between cost estimates and the project budget? 4 years 3 months ago #22596

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Lisa,

I would recommend to refer to Figure 7-8 from the PMBOK Guide to better understand the difference between the two. From there you can see that cost estimates can be derived for each activity, and (by cost aggregation) work package. When you sum up work package cost estimates and contingency reserves (which are also a form of cost estimates), you get the cost baseline. This plus the management reserves provide you with the project budget.

Does that help you clarifying the difference between the two concepts?

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
Last edit: by Gabriella Dellino, PMP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login