which contract has high Risk for buyer
CR
TM
FP

What i know is CR High TM Medium FP low
Please tell me i am right or wrong

Re:Type of Contract--Procurement Management 15 years 4 months ago #104

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1992
  • Karma: 121
  • Thank you received: 616
Arslan,

We explain this in detail in episode E12.01 Plan Procurements.

Please watch that episode for the explanation. We show a table that explains who (buyer or seller) has more risk for each contract.

Also, here are the official abbreviations for the contracts:
Firm Fixed Price: FFP
Fixed Price Incentive Fee: FPIF
Fixed Price Economic Price Adjust: FP-EPA
Cost Plus Fixed Fee: CPFF
Cost Plus Incentive Fee: CPIF
Cost Plus Award Fee: CPAF
Time and Material: T&M
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Type of Contract--Procurement Management 15 years 4 months ago #109

  • Arslan Hamid
  • Arslan Hamid's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 21
  • Thank you received: 0
I am preparing for PMBOK3 and i have your mp3 format podcast.Can you please explain me which contact got the more risk according to buyer prespective...
What i have learn
CR High
TM Medium
FP Low

Thanks

Re:Type of Contract--Procurement Management 15 years 4 months ago #111

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1992
  • Karma: 121
  • Thank you received: 616
Arslan,

I apologize! I didn't realize that you had the 3rd edition.

Please also disregard the abbreviations of the contracts that I mentioned earlier. They are from the 4th edition.

So under this light, you are right that FP = low, TM = medium and CR = high from the buyers perspective.

You can also read the following article - they explain each contract type and the risk involved:

zo-d.com/blog/archives/taking-the-pmp-ex...-contract-types.html
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Type of Contract--Procurement Management 15 years 4 months ago #113

  • Arslan Hamid
  • Arslan Hamid's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 21
  • Thank you received: 0
Thanks Please reply me another question regarding contract as well
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login