Correct Answer is A.
Thanks Carlos, that is the correct answer!
Prioritization of work is not solely based on the customer value. There are other factors to consider, such as risks, dependencies between user stories, and resource availability. Considering human resources availability while planning the sprint would most likely have helped the team to avoid the situation described in the scenario.