fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Free PMI-ACP® Exam Sample Question of the Week

Free PMI-ACP® Exam Sample Question of the Week 6 years 2 months ago #15420

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

At the daily standup meeting, the agile team has raised an impediment where one of the developer's line manager has withdrawn the developer to complete previously committed tasks on another project. As a result, the team will be unable to meet their sprint goal.

What should have been done differently to avoid this situation?

A. The team should have considered human resources availability while planning the sprint.
B. The team should have worked faster than usual during the sprint before the developer was withdrawn.
C. The project should have had a large agile team to compensate for the unplanned impediments.
D. The line manager should not have let the developer work on the new agile project in the first place.

Hint: Dependencies based on people are sometimes overlooked

Watch out for the Answer by the end of the week!

Free PMI-ACP® Exam Sample Question of the Week 6 years 1 month ago #15478

  • Carlos Piepp
  • Carlos Piepp's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
a

Free PMI-ACP® Exam Sample Question of the Week 6 years 1 month ago #15491

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Correct Answer is A.

Thanks Carlos, that is the correct answer!

Prioritization of work is not solely based on the customer value. There are other factors to consider, such as risks, dependencies between user stories, and resource availability. Considering human resources availability while planning the sprint would most likely have helped the team to avoid the situation described in the scenario.


All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI)®. As a PMI® Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.

“PMI” and “PMI-ACP” are registered marks of Project Management Institute, Inc.
Moderators: Yolanda MabutasJohn Paul BugarinSameer MendaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login