I 'm going through some mock exam questions and came across this one that I'm questioning the answer given. The question is as follows:
A scrum team is distributed geographically in 2 different, but overlapping, time zones. When team members in London are starting their working day, those in Riga are more than halfway through the morning. As the ScrumMaster, how would you advise the team to conduct daily scrum meetings?
A. By asking and answering the 3 questions by email
B. With regular conference call at the beginning of the London members' day
C. With regular conference call at the beginning of the Riga members' day
D. By tailoring the framework and cutting out the daily scrum
I answered B, but the answer sheet stated C, which I don't understand because if the meeting started at the beginning of the Riga members' day then the London team members wouldn't even be in the office. Am I missing something her or can someone explain to me why C is the best answer?
Thanks.