fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 5 years 2 weeks ago #18920

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


You are leading a project to build an oil pipeline in a foreign country, and you are looking for local contractors to outsource some of the construction work. You are in the process of preparing the bid package for prospective sellers. Which of the following documents would you leave out of the package?

A. Request for proposal
B. Statement of work
C. Independent cost estimates
D. Source selection criteria

HINT: To answer this question correctly, you need to consider the flow of information between the buyer and prospective sellers before the procurement selections are made.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation
The correct answer is C.

Preparing the bid package for prospective sellers implies you are carrying out the Plan Procurement Management process. Bid documents (with the request for proposal (RFP) among them), procurement statement of work (SOW), source selection criteria, independent cost estimates are among the outputs of this process. These documents are also among the inputs to the Conduct Procurements process. However, not all of these documents are provided by the buyer to the prospective sellers. Sometimes, to benchmark procurements, the buying organization develops independent cost estimates either internally or using external resources such as a professional estimator. Buyers do not usually provide these estimates to the prospective sellers since a benchmark range may prejudice the sellers into proposing prices that do not actually work for their business model and resources. The buyer uses these benchmark estimates principally to verify if bids are reasonable, or if a large number of outliers indicate an issue with procurement processes or communications. Thus, of the choices provided, leaving the independent cost estimates out of the bid package makes the most sense and is, therefore, the best answer to the question asked.

Details for each option:

A. Request for proposal
Incorrect. The RFP, along with the request for information (RFI), and request for quotation (RFQ) are all bid documents that directly invite prospective sellers to bid for the project so that they may be included in the selection analysis. One of these types of documents should be in the bid package.

B. Statement of work
Incorrect. The SOW describes in detail the required products, services, or results. Without such detail, prospective sellers may not be able to determine if they can fulfill the requirements. Either the SOW or a similar document, terms of reference (TOR), should be in the bid package.

C. Independent cost estimates
Correct. The buying organization develops independent cost estimates either internally or using external resources such as a professional estimator. Buyers do not usually provide these estimates to the prospective sellers, because they are primarily for internal benchmarking purposes.

D. Source selection criteria
Incorrect. Competitive selection methods may require sellers to invest a large amount of time and resources upfront. Therefore, it is a good practice to include the evaluation method in the procurement documents, so bidders know how they will be evaluated.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 477-479, 485
The following user(s) said Thank You: Chima Ifeajuna
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login