fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 5 years 4 weeks ago #18805

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


Two new team members have just joined the project you are leading. The project is large and involves many stakeholders. You want to get the new team members up to speed with the overall dynamics of the project and engage effectively with the project stakeholders. What should you do?


A. Ask the team members to record any issues they encounter into the issue log
B. Review the stakeholder register with the new team members
C. Schedule a meeting with the new team members and all project stakeholders
D. Submit a change request to update the stakeholder engagement plan

HINT: What document lists people or organizations either positively or negatively impacted by a decision, activity or outcome of the project?

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation
The correct answer is B.

The stakeholder register is a project document that contains all current information about the stakeholders. The stakeholder register includes stakeholder identification information, assessment information, and stakeholder classification. It is used by the project team to maintain information about the stakeholder's expectations and interests with the project. By reviewing the stakeholder register with the new team members, the project manager can provide them with the information about each project stakeholder, politics surrounding the project, and other relevant details about the project and the stakeholders that may help the new team members to get up to speed with the overall dynamics of the project and engage effectively with the project stakeholders.

Details for each option:

A. Ask the team members to record any issues they encounter into the issue log
Incorrect. The issue log is an internal document where current issues are recorded and monitored. This document is used to manage issues that need to be resolved on the project but does not contain information about the stakeholders or their potential influence on the project and, therefore, would not be helpful in the effective engagement of the team members with the project stakeholders.

B. Review the stakeholder register with the new team members
Correct. The stakeholder register is a project document that includes identification information, assessment information, and the stakeholder classification status. This document would provide the new project team members a sense of who the key stakeholders are and the overall dynamics of the project, thus helping the new team members engaging with the stakeholders.

C. Schedule a meeting with the new team members and all project stakeholders
Incorrect. While scheduling a meeting with the new team members and all project stakeholders could help the project manager in achieving the goal stated in the scenario, scheduling a meeting with 'all' project stakeholders on a large project seems unrealistic and is an ineffective use of project resources. Another answer choice represents a more plausible action to address the question asked.

D. Submit a change request to update the stakeholder engagement plan
Incorrect. The stakeholder engagement plan describes the strategies and actions required to promote the productive involvement of stakeholders in the project. While a change request is required to update the plan, solely submitting a change request to update the stakeholder engagement plan without specifying what exactly is to be updated is unlikely to help the new team members to effectively engage with the project stakeholders.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 525
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login