fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week!

Free PMP® Exam Sample Question of the Week! 5 years 2 months ago #18492

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


Ada, the project manager, is meeting with a customer for initial discussions about a software implementation project. At the end of the meeting, the customer asks Ada for a general estimate of the project duration. Based on experience with three similar projects with roughly the same scope, Ada estimates an 8-10 month implementation time frame. What estimation technique is Ada basing her duration projection on?

A. Expert judgment
B. Three-point estimating
C. Analogous estimating
D. Bottom-up estimating
HINT: Identify the estimating technique that compares a project to a previous, similar project.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation
The correct answer is C.

Ada is using historical duration information from comparable projects to estimate the duration of a future project. This gross value estimating approach is called analogous estimating and is frequently used to provide a ballpark figure when there is a limited amount of detailed information available about the project.

A. Expert judgment
Incorrect. In a sense, Ada is using expert judgment due to her experience, but because she is basing her duration estimate on three similar projects, analogous estimating is a better answer choice.

B. Three-point estimating
Incorrect. Three-point estimating would require Ada to collect optimistic, pessimistic and most likely duration estimates to calculate a projected time frame for the work. Since Ada was required to provide a 'general' estimate on the spot, analogous estimating is a better technique since she is familiar with the time it took to complete similar projects with similar scope.

C. Analogous estimating
Correct. Ada is using analogous estimating, which is a common technique used to provide a rough estimate on a future project based on parameters from a previous, similar project. In this scenario, duration from the three previous projects was used as the basis for estimating the duration of this project.

D. Bottom-up estimating
Incorrect. Bottom-up estimating would be the most thorough technique but would take the longest time. Also, this method is typically used when estimates cannot be made with a high degree of confidence. Since Ada has historical information available, analogous estimating would satisfy the customer's request for a 'general' estimate.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 200
The following user(s) said Thank You: Hidayat Ullah Khan, Ryan Hileman
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question of the Week! 5 years 1 month ago #18671

  • Syed Sadaqain
  • Syed Sadaqain's Avatar
  • Visitor
  • Visitor
Analogous Estimating
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login