fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 6 years 3 months ago #14791

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator

You are managing a renovation project of a vintage house which is to be completed in 12 months on a budget of $100,000. You are 6 months into the project, and you have spent $60,000, but only 40% of the work is completed. How much more will it cost to complete the renovation if the cost performance remains unchanged?

A. $171,940
B. $120,000
C. $149,254
D. $89,254

HINT: Determining how much more it will cost to finish the project is the ETC.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is D.

The total budget or BAC is $100,000. The cost so far or AC is $60,000. You have completed 40% of the work which is the EV or 40% of $100,000 or $40,000. The question is asking for the cost to complete the renovation or the ETC. The remaining calculations are as follows:
ETC = EAC - AC
EAC = BAC / CPI
CPI = EV / AC or 40,000 / 60,000 = 0.67
EAC = 100,000 / 0.67 = 149,254
ETC = 149,254 - 60,000 = 89,254 or the cost required to complete the renovation.

A. $171,940
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula
EAC = AC +[(BAC - EV) / (CPI x SPI)].


B. $120,000
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula
EAC = AC + BAC - EV.


C. $149,254
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula
EAC = BAC / CPI.


D. $89,254
Correct. The cost required to complete the project is $89,254. The value was derived using ETC = EAC - AC utilizing the formula EAC = BAC / CPI to calculate EAC.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 267
The following user(s) said Thank You: Seni Adeyemi
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question of the Week 6 years 3 months ago #14827

  • Usen Sunday Umoekah
  • Usen Sunday Umoekah's Avatar
  • Visitor
  • Visitor
Thanks for your details answer to the question.
I will like to know more on simulation sample questions and answers.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login