fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: PERT/Standard Deviation Question

PERT/Standard Deviation Question 6 years 4 months ago #14611

  • Brandon A
  • Brandon A's Avatar Topic Author
  • Visitor
  • Visitor
Hi All,

I've been working through some sample questions over at Oliver Lehman's PM site. I came a across #27 in his 100 free PMP questions. I come from a quality background where we determine standard deviation empirically from a data set so these equations to approximate variance and SD are working a part of my brain that must be dormant. How do we arrive at 5.2 from the data set given? Any help is appreciated, see the problem below. Thanks!

A project manager made 3-point estimates on a critical path along a sequence of activities A through E and found the following results:



Assuming ±3 sigma precision level for each estimate, what is the calculated standard deviation of the allover path?

App. 4.2 days
App. 5.2 days
App. 6.2 days
You can not derive the path standard deviation from the information given.
Last edit: by John Paul Bugarin.

PERT/Standard Deviation Question 6 years 4 months ago #14646

  • Kunwar Goyal
  • Kunwar Goyal's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
hi,
there will no influence of the activity ,if we choose activity B,C and D
so calculate the SD for A and E =((35-17)/6)+((24-12)/6)=3+2=5
Pl correct me if I am wrong

PERT/Standard Deviation Question 6 years 4 months ago #14677

  • Brandon A
  • Brandon A's Avatar Topic Author
  • Visitor
  • Visitor
Me again,

I found a similar problem and explanation which helped me figure out this one.

You must first calculate the standard deviations of each sequence activity, A through E, using (P-O)/6. Square each standard deviation to yield the variance (Variance = SD^2). Add all the sequence activity variances together then take the square root of the sum. This will yield 5.19... which rounds to 5.2. You could then express the schedule as 83.1 +/- 5.2 days.

I just passed the PMP today but couldn't let this question go.

Thanks

PERT/Standard Deviation Question 6 years 4 months ago #14679

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Thanks for clarifying

[email protected] 4 years 2 months ago #23294

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
Thank you! It seems like the PERT weighted values in the table are included to throw us off!

[email protected] 4 years 2 months ago #23540

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
I couldn't let it go either. Thank you.

PERT/Standard Deviation Question 3 years 11 months ago #24876

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
in the question it state +/- 3 sigma

PERT/Standard Deviation Question 3 years 11 months ago #25335

  • Amit Kumar
  • Amit Kumar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Thank Brandon...was searching for this.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login