fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 6 years 10 months ago #12824

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project started on April 1st, 2013 is expected to be completed by March 31st, 2014. During a project review on September 30th, 2013 it is determined that the total Actual Cost is $17.6 Million, the total Earned Value is $12.3 Million, and the total Planned Value is $12.8 Million. How much is the Schedule Variance?

A. $5.2 Million
B. $0.5 Million
C. -$0.5 Million
D. -$4.8 Million

HINT: SV = EV - PV

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

Schedule Variance = Earned Value - Planned Value = $12.3 Million - $12.8 Million = -$0.5 Million.
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login