fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 7 years 1 month ago #12034

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are managing a bridge construction project. You have completed half of the project work. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1,000 on the project. What is the CPI?

A. 0.5
B. 4
C. 0.4
D. 1

HINT: CPI is the Cost Performance Index.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.

CPI = EV/AC EV = $400, AC = $1,000, PV = $500
Therefore CPI = 0.4
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login