TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #11909

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project manager decides to start the schedule activity only after the predecessor activity finishes. Which type of relationship exists between the activities?

A. Start-to-Finish
B. Finish-to-Finish
C. Finish-to-Start
D. Start-to-Start

HINT: This is the most common type of activity relationship.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

A finish-to-start relationship means the dependent activity cannot start until the first activity is finished.
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login