TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 7 years 5 months ago #10844

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are managing a bridge construction project. Half of the project work has been completed. The total planned cost at this stage was $2.5 million. The actual physical work that has been completed at this stage is worth $2.4 million. You have already spent $5.0 million on the project. What is the schedule variance?

A. $100,000
B. -$100,000
C. $2.6 million
D. $2.5 million

HINT: SV = EV - PV

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

SV=EV-PV = $2.4 million - $2.5 million = -$100,000
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question of the Week 7 years 5 months ago #10912

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
The selection B has typo, it is not -100,000 but as written -100,00 (missing a zero)
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login