TOPIC: PERT PMP Question

PERT PMP Question 7 years 6 months ago #10572

  • Anurag Singh
  • Anurag Singh's Avatar Topic Author
  • Visitor
  • Visitor
Can somebody please provide explanation to the following PERT Question from Oliver Lehmann's free sample questions:
Together with your team, you applied three-point estimation on a critical path which consists of two activities.
The following duration uncertainties are all calculated assuming a ±3sigma confidence interval.
The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? 94
o 21 days
o 30 days
o 42 days
o No statement is possible from the information given.

The correct answer is 21 days, but I am not sure how arrive at this answer. Please advise.

PERT PMP Question 5 years 8 months ago #16750

  • Anonymous
  • Anonymous's Avatar Topic Author
  • Visitor
  • Visitor
First P-O = 18
Second P-O = 24
2P-2O = 42
So, P-O = 21

PERT PMP Question 5 years 1 week ago #19022

  • Jenny
  • Jenny's Avatar Topic Author
  • Visitor
  • Visitor
Can somebody explain this a little bit more? Still not quite understand.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login