TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 8 years 6 months ago #7400

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

You are developing your project's Human Resource Management Plan. Your sponsor asked you to take the historical information from previous projects to determine this project's human resource roles and responsibilities. Which of the following sources contains this information?

A. Organizational Process Assets
B. Enterprise Environmental Factors
C. Project Management Plan
D. Project Charter

HINT: Look for the keyword phrase 'historical information'. Only one of these options contains historical information.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is A.

Organizational Process Assets contain historical information about previous projects.
The following user(s) said Thank You: Jason

Free PMP Exam Sample Question of the Week 8 years 6 months ago #7412

  • Otoku Onajite
  • Otoku Onajite's Avatar
  • Visitor
  • Visitor
Thank You
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login