TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 8 years 11 months ago #6586

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 397
  • Karma: 16
  • Thank you received: 130


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which of the following processes would you use in a project to reprioritize the remaining work based on resource availability?

A. Control Schedule
B. Develop Schedule
C. Estimate Activity Resources
D. Estimate Activity Durations

HINT: This is usually done in the monitoring and controlling process.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is A.

The Control Schedule Process is used to reprioritize the remaining work in a project. This is done to properly allocate remaining resources based on their availability.
The following user(s) said Thank You: Jideofor Ebeogu

Free PMP Exam Sample Question of the Week 8 years 11 months ago #6601

  • Anirban Banerjee
  • Anirban Banerjee's Avatar
  • Visitor
  • Visitor
Great question! Thank you. Anirban
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login