You are the project manager on a new nationwide telecom network. Your client told you that conformance to the highest quality standards is mandatory but this client is new to the telecom industry and is unable to provide specific technical parameters. Your client said that the network's conformance should be graded against the leading telecom operator in the country. What is this practice called?
A. Cost-Benefit Analysis
B. Pairwise Comparison
C. Benchmarking
D. Quality Metrics
HINT: Your client has an existing telecom network in mind against which they are setting their quality requirements.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is C.
This is an example of benchmarking. According to the PMBOK Guide, "Benchmarking involves comparing actual or planned project practices to those of comparable projects to identify best practices, generate ideas for improvement, and provide a basis for measuring performance. These other projects can be within the performing organization or outside of it and can be within the same or in another application area."