Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
You managed a project with over 60 team members to design a new sports car. In the project kickoff meeting you assured the team that good performers would be rewarded. At the project closing meeting, you only awarded incentive bonuses to two team members. A client who was present asked why only two team members were rewarded with bonuses. What did you miss while defining rewards and recognition?
A. You didn't realize recognizing cultural differences may offend people
B. You defined objectives on work that was supposed to performed
C. You set criteria for rewards that made the team over confident
D. You made the targets unachievable on the project
HINT: Team recognition should be based on individual tasks that are achievable and clear.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is D.
The entire team worked together to complete the project but only two members were rewarded. This implies that the targets were unachievable and that the expectations set by you were unrealistic.