You developed alternative project schedules based on the best-case and worst-case scenarios. You want to keep these alternative schedules stored somewhere, in case of changes in project resources. Where would you store the alternative schedules?

A. Schedule Baseline
B. Schedule Data
C. Project Documents
D. Project scope statement

HINT: Alternative schedules are output of the Develop Schedule process. Look for the outputs of the Develop Schedule process to see where these schedules are stored.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

Schedule data contains alternative schedules such as best-case or worst-case scenarios. This is an output of the Develop Schedule process.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login