fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: PM Prepcast Pre-Course Self-Assessmen (Q11)

PM Prepcast Pre-Course Self-Assessmen (Q11) 9 years 8 months ago #5297

  • Jonathan Robinson
  • Jonathan Robinson's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
"Question 11: Work has been completed on your Fixed Price Incentive
Contract. The original contract was for $55,000, of which $50,000 is target
cost and $5,000 is target profit. A share ratio of 50/50 has been agreed
upon. The actual cost incurred on the project is $48,000. How much is the
final price?"

I've reviewed the answer key and understood the answer; however, my question is with the original problem. The problem outlines the the work has been completed on a 'Fixed Price Incentive' - after reviewing definitions in PMBOK 5th pg363-4, I wonder if this should read 'Cost Plus Incentive Fee Contract' instead as 'buyer and seller share costs from the departures based upon a prenegotiated cost-sharing formula'?

If this presumption is incorrect - would you be able to briefly explain the differences between these contracts?

PM Prepcast Pre-Course Self-Assessmen (Q11) 9 years 8 months ago #5298

  • Ahmed Amin
  • Ahmed Amin's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 300
  • Karma: 10
  • Thank you received: 73
Hi Jonathan,

I agree with your conclusion that the question is describing a "Cost Plus Incentive Fee Contract" as fixed price contracts don't have cost-sharing formulas.
Ahmed Amin Abdullah, PMP
Community Moderator

PM Prepcast Pre-Course Self-Assessmen (Q11) 9 years 8 months ago #5308

  • Steve Sandoval
  • Steve Sandoval's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 49
  • Thank you received: 11
I agree with Ahmed. Share ratios show up with Cost Plus Incentive Fee contracts. This is a "bad" (or at least confusing) question!
Steve Sandoval, PMP
Community Moderator

PM Prepcast Pre-Course Self-Assessmen (Q11) 9 years 8 months ago #5309

  • Jonathan Robinson
  • Jonathan Robinson's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thank you for your response, Ahmed and Steve. I will mark this one as odd.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login