fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week!

Free PMP Exam Sample Question of the Week! 9 years 8 months ago #5232

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project?

A. $300
B. $40
C. $20
D. $10


Hint: Apply the formula to calculate Cost Variance.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

The formula to calculate Cost Variance (CV) is: CV=EV-AC. Therefore, CV = 100 - 90 = 10.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login