Ok my bad, I assume Qualified Sellers List to imply Pre-Qualified Sellers List as he was looking to save time. I have to stop making assumptions

. Thanks for clearing my doubts Ahmed! It’s been very helpful to point out some of my typical mistakes to avoid them for the exam.
Q. Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?
A The project was terminated early. At that time, it was over budget and ahead of schedule.
B The project has produced additional deliverables which were originally not required.
C The project has evidently been finished under budget and behind of schedule.
D The project has evidently been finished over budget and ahead of schedule.
I marked D, the answer is A. Any idea how these numbers could indicate if a project was terminated early instead of being finished? Is it because when the project would be finished the SPI will
always be 1.00?