fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 10 years 2 months ago #4630

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:

You are managing a construction project and your project budget is $20,000. You have spent $17,000 so far and the project is 75% complete. A new project budget of $25,000 has been approved. What should your cost performance be if you want to complete your project within the new approved budget?

A. 1.667
B. 0.882
C. 0.625
D. 0.521


Hint: Calculate the TCPI based on EAC.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is C.

Since the BAC = $20,000 and the project is 75% complete, the EV = (BAC x % complete) = $15,000. Now you need to calculate your desired future cost performance, you should calculate the TCPI based on EAC by using the formula TCPI = (BAC-EV)/(EAC-AC) = (20,000 - 15,000) / (25,000 - 17,000) = 5,000/8,000 = 0.625.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login