Hi,
I don't understand how this answer was calculated for the question from Oliver Lehmann's free 75 question test.
Can anyone please enlighten? The correct answer is B ie. approx. 5.2 days.
27. A project manager made 3-point estimates on a critical path and found the following results: (Check attached table below)
Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?
(A) App. 4.2 days
(

App. 5.2 days
(C) App. 6.2 days
(D) You can not derive the path standard deviation from the information given.