Question:

The Change Control Board reviews all of the change requests for every project in your company. This board follows all the recommended activities outlined in the PMBOK Guide. Based on this scenario, which of the following would not be performed by the Change Control Board?

A. Documenting change request decisions and recommendations
B. Reviewing change requests
C. Creating change requests
D. Accepting or rejecting change requests


Hint: What specific functions does the Change Control Board perform according to the PMBOK Guide?


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is C.

According to the PMBOK Guide, the Change Control Board is responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project, with all decisions and recommendations being recorded. It is up to the individual project team members to actually create the change requests.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login