fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 10 years 5 months ago #4342

  • Anne B
  • Anne B's Avatar Topic Author
  • Visitor
  • Visitor


Question:

You have just been hired as the operations manager for a telecommunications company. You are tasked with improving the company's services and operations and a team of 20 engineers report to you. During your first week at this company, you found that the engineers spend at least 80% of their time responding to unexpected requests for information from different stakeholders. Because of this, your engineers cannot focus on the operations, which is resulting in frequent network outages. As the project manager, what should you do first to resolve this problem?

A. Tell the engineers to stop responding to unexpected requests since they are not covered in the Communications Management Plan
B. Push the engineers to respond to all the requests faster so that they are able to perform their regular duties
C. Perform all project communications yourself and let the engineers focus on the operations
D. Analyze the stakeholder requirements and review the Communications Management Plan


Hint: You need to further investigate the problem.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

You are clearly having issues in your Control Communications process. Control Communications is the process used to make relevant information available to project stakeholders, as planned to ensure the information needs of the stakeholders are met. The focus here is mainly in the Controlling process group. However, since your team is spending 80% of their time handling unexpected information requests, clearly something is terribly wrong. You should further investigate the issue by analyzing stakeholder requirements and reviewing the Communications Management Plan.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login