Here is the question: (source:
www.oliverlehmann.com/pmp-self-test/75-free-questions.htm
)
9. In order to speed up a project, you made a decision to fast-track a phase currently performed with
five team members, and another one which was planned to begin in four weeks time with another
five team members. Which of the following activities should you do first?
A. Make sure that all exit criteria of the consecutive phase have been met to ensure theflow of
communications in a team situation which is more complex by a factor of 2.
B. Make sure that all entry criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical aptness.
C. Make sure that all exit criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical performance.
D. Restructure your team and delegate tasks in order to ensure the flow of communications in a
team with the number of communication channels increased by a factor of 4.5.
The answer is D. The explanation is: Additional communication channel is the first step for the fast-track to be successful. Instead of the current communication channel of 5 * (5-1) / = 10 , the communication channels need to be increased to 10 * (10-1) / 2 = 45. So there is a factor of 4.5.
Then here the problem is : This kind of calculation assumes that the current 5 members including the PM. This assumption is already questionable as there is so such statement. And what's more, when talking about the new team, the 5 members doesn't include the PM. (the same PM is in charge of both projects as he can make the decision for both phases)
I think a more logical calculation should be: In the first phase, the total channel should be: 6 * (6-1) = 15. With the need of more communication channel, the total channel should be: 11* (11-1) = 55. Of course in this case no option given is correct.
All inputs are welcome