Question:

You are currently performing quality assurance on your project by conducting a Quality Audit. Which of the following is not an objective of a Quality Audit?

A. Share the good practices introduced or implemented in similar projects in the organization and/or industry
B. Document the effectiveness of the Risk Management process
C. Identify all the good/best practices being implemented
D. Identify all the gaps/shortcomings


Hint: Think about the specific knowledge area in which you conduct the Perform Quality Assurance process.


All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation: http://free.pm-exam-simulator.com

The Correct Answer is B.

The Perform Quality Assurance process is conducted in the Quality Management knowledge area, not the Risk Management knowledge area. Although documenting the effectiveness of the Risk Management process is an important activity, it is performed in the Risk Management knowledge area, not the Quality Management area. All remaining answer choices are specific objectives of the Quality Audit.
Moderators: Yolanda MabutasAnne BMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login