TOPIC: network diagram

network diagram 12 years 10 months ago #2673

  • Olaoluwa Ibilola
  • Olaoluwa Ibilola's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Karma: 1
  • Thank you received: 0
Kindly take look at this question and clarify accordingly:
The activity “Ship Container” in your network diagram has an early
start of day 17, a late start of day 22 and a late finish of day 37. What is the activity duration?
A.) 15 days
B.) 16 days - Correct Answer
C.) 59 days
D.) 14 days

Based on the Formula guide the formula says Activity Duration=EF - ES + 1 or LF - LS + 1..when translated AD= 37-22+1 = 16. Based on Rita 6th Edition the answer will be 15 because ES = 0.

kindly clarify this confusion.

Re:network diagram 12 years 8 months ago #2732

  • Richard
  • Richard's Avatar
  • Visitor
  • Visitor
I'd really like the answer to this as well. You only get one correct answer on the test. I use Rita's book as well. Do we use base "0" or base "1" for calculations? The can't both be correct. Which one does PMI want?

Re:network diagram 11 years 6 months ago #3344

  • Jimmy Varghese
  • Jimmy Varghese's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
  • Thank you received: 0
I came across the same question. From the network diagram node, i know its answer should be 15. But why is it 16?

What is PMI specific answer for this? Why do we add a "1" to activity duration? Because when i draw my network diagram for my projects, for e.g. if duration is 5 days and activity LS is 20th May i consider LF to be 24th and not 25th May.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login