The project sponsor asks for a copy of the document that contains the description, owner, source, priority, and status of product requirements.
Which project document is the project sponsor requesting?
A. The requirements management plan
B. The requirements traceability matrix
C. The scope management plan
D. The work breakdown structure (WBS)
HINT: The document described by the sponsor in the scenario links product requirements from their origin to the deliverables that satisfy them.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
free.pm-exam-simulator.com/
and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
In this scenario, the project sponsor requested a document that provides specific information about the product requirements of your current project. The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them.
Typical attributes used in the requirements traceability matrix may include a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status, and status date.
Additional attributes to ensure that the requirement has met stakeholders' satisfaction may include stability, complexity, and acceptance criteria.
Details for each option:
A. Incorrect. The requirements management plan is a component of the project management plan that describes how requirements will be analyzed, documented, and managed. The requirements management plan does not have detailed information regarding each of the product requirements.
B. Correct. The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. Typical attributes used in the requirements traceability matrix may include a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status, and status date. The document the sponsor is requesting is the requirements traceability matrix.
C. Incorrect. The scope management plan is a component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated. The scope management plan does not contain the details the project sponsor is seeking, making this an incorrect answer.
D. Incorrect. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. The WBS represents the project work in work packages and does not provide the details of the document the sponsor requested.
Reference:
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Project Management Institute Inc., 2021:
4.6.6 VISUAL DATA AND INFORMATION
2.6.2.1 Requirements
Process Groups: A Practice Guide, Project Management Institute Inc., 2023,
5.3 Collect Requirements
9 Inputs and Outputs