You are part of a project team designing a new type of vehicle. You are about to begin work on a work package for the braking system of the vehicle and want to review the acceptance criteria before starting the work.
Where can you find this information?
A. Project management plan
B. Activity attributes
C. Requirements documentation
D. The WBS dictionary
HINT: This document is developed during the Create WBS process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
free.pm-exam-simulator.com/
and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is D.
Details for each option:
A. Incorrect. The project management plan is the document that describes how the project will be executed, monitored and controlled, and closed. While the information you seek is available in the project management plan (within the WBS dictionary which is part of the scope baseline which, in turn, is a component of the project management plan), there is another answer choice that more accurately addresses the question asked. When choosing between two seemingly correct answer choices, typically the more specific choice is the correct answer.
B. Incorrect. Activity attributes are the additional details associated with each schedule activity that can be included within the activity list. Activity attributes may include activity codes, predecessor activities, logical relationships, resource requirements, etc. However, the acceptance criteria for work packages are not among activity attributes.
C. Incorrect. As part of project planning, requirements are collected to develop the scope of the project. The requirements documentation describes how these individual requirements meet the business need for the project.
D. Correct. The WBS dictionary is a supporting document for the WBS and provides detailed information about each component in the WBS. Acceptance criteria for each of the work packages are included in the WBS dictionary, making this choice the best answer to the question asked.
Reference:
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 162