TOPIC: Requirements and configuration management plans

Requirements and configuration management plans 3 years 3 months ago #27992

  • Jorge Rodriguez
  • Jorge Rodriguez's Avatar Topic Author
  • Offline
  • User
  • User
  • Thank you received: 0
Hello,

Changes to the configuration and requirements management plans , do they go through the change control board? what about changes to performance measurement baseline (PMB)?

thank you in advance for your help.

Requirements and configuration management plans 3 years 3 months ago #28014

  • Stegg Hooks
  • Stegg Hooks's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
The change management plan, configuration management plan, requirements management plan, and performance measurement baseline are components of the project management plan—dependencies of the project. Therefore, an approved change request can modify the formally controlled project management plan components or project documents.
Last edit: by Stegg Hooks.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login