fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 3 years 11 months ago #25031

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


You are about to start planning for a large and complex project. Due to the size of the project along with the regulatory and environmental considerations, the development of a detailed project management plan will be critical.

As a starting point for initial project planning, what is the first thing you should do?

A. Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment
B. Review the project charter to understand the high-level information about the project
C. Begin the process of identifying stakeholders so they can be engaged as necessary for project planning
D. Share the project scope statement with the project team for a common understanding of project deliverables

HINT: The Initiating Process Group has been completed, and the Planning Process Group is about to begin.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation
The correct answer is B

The question states that project planning is about to begin which suggests that project initiation has been completed. The project charter is created during the Develop Project Charter process as part of project initiation. The project team uses the project charter as a starting point for initial project planning. The type and amount of information in the project charter varies depending on the complexity of the project and the information known at the time of its creation. At a minimum, the project charter should define the high-level information about the project that will be elaborated on in the various components of the project management plan.

Details for each option:

A. Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment
Incorrect. For large projects, like the one described in the scenario, the kick-off meeting is usually associated with the end of project planning and the start of execution. Therefore, conducting a kick-off meeting is not likely to be the first activity for the initial planning of this project.


B. Review the project charter to understand the high-level information about the project
Correct. Besides authorizing the project and naming the project manager, the project charter documents the high-level information about the project. The type and amount of information in the project charter varies depending on the complexity of the project and the information known at the time of its creation. At a minimum, the project charter should define the high-level information about the project that will be elaborated on in the various components of the project management plan. Reviewing the project charter is the most reasonable first thing for you to do as a starting point for initial project planning.



C. Begin the process of identifying stakeholders so they can be engaged as necessary for project planning
Incorrect. The Identify Stakeholder process is part of the Initiating Process Group. The question states that project planning is about to begin which suggests that the processes associated with the Initiating Process Group have already been completed. Therefore, the identification of stakeholders is not the first activity to be completed for project planning.

D. Share the project scope statement with the project team for a common understanding of project deliverables
Incorrect. The project scope statement is an output of the Define Scope process, which is one of the processes in the Planning Process Group. As such it is not yet available at the start of project planning. Therefore, this answer choice can be eliminated.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 83, 81
The following user(s) said Thank You: Anu Maletira
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question 3 years 11 months ago #25150

  • SHALI SUNDARAN
  • SHALI  SUNDARAN's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi

I have purchased the prepcast simulater of 2020, so my query is the existed simulater will be updated for 2021, if its valid expires in Jan, 2021. Or do v need renew for 2021.

Free PMP® Exam Sample Question 3 years 11 months ago #25261

  • N Balasundar
  • N Balasundar's Avatar
  • Visitor
  • Visitor
very well explained

Free PMP® Exam Sample Question 3 years 11 months ago #25282

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
@Shali, that’s a question for the customer services team. Have you contacted them to ask about your situation?
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login